CONSTRUCTION OF LE VILLAS RESIDENCE

Le-Villas-Saiyuan-Phuket-LuxuryVillas-Progress-Update

Construction Symbol

PROJECT COMPLETION

 
 
Complete concrete 1st floor
Complete concrete 1st floor

September 30, 2019

Complete concrete 1st floor V16, V17 and foundation of V17, V18

September 15, 2019

Start the foundation work for V18-V19

August 15, 2019

Pest & termite control
Eco friendly Anti Termite Treatment by laying sub surface Piping Network. Termite Treatment through piping method designed to effectively treat the area under concrete slabs before flooring is done.

July 15, 2019

Sanitary & Piping work
Installing waste pipes for basins, sinks and toilets, including installing pipe work for grey-water used to flush toilets.

June 15, 2019

Footing work V16-V20

May 15, 2019

Complete the main drainage concrete pipe and part of the project access road to ready for construction. All preliminary work has been prepared and complete foundation work of villa V16 V17 V18.

April 15, 2019

Land clearing and Excavation Work. The land site clearing and grubbing is generally performed concurrently in order to ready the site for topsoil stripping and bulk excavation. Since clearing and grubbing happens as the first work item on the project, it is usually critical to the project schedule. Therefore, our Construction Supervisor understands the process of clearing and grubbing in order to prepare contour of the project and later separation of each plot of villas.

April 1, 2019

Started with a beautiful hillside land plot. Le Villas & Residence project has started with a beautiful hillside land plot of total 10,000 sq.m. with the concept design and land preparation.