CONSTRUCTION OF LE VILLAS RESIDENCE

Construction Symbol

PROJECT COMPLETION
June 8, 2020
V15 Reinforced concrete 2nd floor and V16 Swimming pool work done
April 25, 2020
V16 – V20 Completion of the buildings.
This 6 Bedrooms pool villa is under interior and the landscape work.
October 26, 2019
V16, V17 complete pool structure and start V16 3rd floor.
V18, V19, V20 complete the 1st floor
September 30, 2019
Complete concrete 1st floor V16, V17 and foundation of V17, V18
September 15, 2019
Start the foundation work for V18-V19
August 15, 2019
Pest & termite control
Eco friendly Anti Termite Treatment by laying sub surface Piping Network. Termite Treatment through piping method designed to effectively treat the area under concrete slabs before flooring is done.
July 15, 2019
Sanitary & Piping work
Installing waste pipes for basins, sinks and toilets, including installing pipe work for grey-water used to flush toilets.
June 15, 2019
Footing work V16-V20
May 15, 2019
Complete the main drainage concrete pipe and part of the project access road to ready for construction. All preliminary work has been prepared and complete foundation work of villa V16 V17 V18.
April 15, 2019
Land clearing and Excavation Work. The land site clearing and grubbing is generally performed concurrently in order to ready the site for topsoil stripping and bulk excavation. Since clearing and grubbing happens as the first work item on the project, it is usually critical to the project schedule. Therefore, our Construction Supervisor understands the process of clearing and grubbing in order to prepare contour of the project and later separation of each plot of villas.
April 1, 2019
Started with a beautiful hillside land plot. Le Villas & Residence project has started with a beautiful hillside land plot of total 10,000 sq.m. with the concept design and land preparation.